Integrated Baseline Management - Including 'design change' from the current schedule in the PMB

Steven WilliamsMember for 21 years 5 months
Created
0
5
0

I have used the 'Maintain Baselines' process to include activities related to approved change from the current schedule in the Performance Measurement Baseline (PMB). when i have checked the PMB following this process (by de-linking the baseline and restoring to the EPS), i have found that the activities that have been coded up and filtered in the process have not all transfereed to the PMB - although the report indicates they have.

 

i am looking for an alternative method that will import all activities coded up for change into the PMB before i assign it to the Current Working Schedule (CWS).