Integrated Baseline Management - Including 'design change' from the current schedule in the PMB
- Created
- 0
- 5
I have used the 'Maintain Baselines' process to include activities related to approved change from the current schedule in the Performance Measurement Baseline (PMB). when i have checked the PMB following this process (by de-linking the baseline and restoring to the EPS), i have found that the activities that have been coded up and filtered in the process have not all transfereed to the PMB - although the report indicates they have.
i am looking for an alternative method that will import all activities coded up for change into the PMB before i assign it to the Current Working Schedule (CWS).
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?