Negative (?) terminal float
In the Open Standard
Emmanuelle PrefolMember for 14 years 10 months
- Created
- 8
- 4
0
At contract award, contractor's programme shows planned completion date = completion date.
The works starts as planned but there is then a contractor's incurred delay of 3 weeks, of which 2 weeks will be absorbed by the TRA, should the 1st progressed then programme show:
1) planned completion date + 1 week and same completion date
2) planned completion date + 1 week and completion date + 2 weeks
Thanks.