Negative (?) terminal float

Emmanuelle PrefolMember for 14 years 10 months
Created
8
4
0

At contract award, contractor's programme shows planned completion date = completion date.

The works starts as planned but there is then a contractor's incurred delay of 3 weeks, of which 2 weeks will be absorbed by the TRA, should the 1st progressed then programme show:

1) planned completion date + 1 week and same completion date

2) planned completion date + 1 week and completion date + 2 weeks

Thanks.
 

 

 

8 replies

Oldest first
  1. 0
    Gary Whitehead ·

    If the delay was the

    If the delay was the responsibility of the contractor (ie no CE), then:

    planned completion date + 1 week and same completion date

     

    If the delay was the responsibility of the client, then:

    planned completion date + 1 week and completion date + 3 weeks

     

    Cheers,

    G

  2. 0
    Emmanuelle Prefol ·

    OK thanks. Delay was

    OK thanks.

    Delay was contractor's responsibility so you advise "planned completion date + 1 week and same completion date"
    Concern I have is that the programme does not "show" delay i.e. current completion date same as initial completion date in contracts data vol.1.

    Also, not understanding, should this be the client responsibility, why the PCD and CD move by the amount of weeks you said.

    Can you suggest any papers/books... that would help in getting a better grasp on PCD, CD and terminal float.

    E.

     

     

  3. 0
    Gary Whitehead ·

    Now I am confused... If there

    Now I am confused...

    If there is a 3 week delay and 2 weeks of that delay are absorbed by TRA, then there must be a net 1 week delay. Why does the current programme not show this delay?

    Is it perhaps because the 3 week delay occured on an activity that was not on the critical path -ie only completion of that activity and not the whole project has been delayed?

     

    If the client delays the project, then this should trigger a CE which ammends the completion date by the full three weeks. -TRA and terminal float belong to the contractor only -they can not be used to reduce a contractor's entitlement to EOT.

     

    The only references I use for NEC contracts are the guidance notes that accompany the standard contract form. I can't recommend a book or anything.

  4. 0
    Emmanuelle Prefol ·

    ... If there is a 3 week

    ... If there is a 3 week delay and 2 weeks of that delay are absorbed by TRA, then there must be a net 1 week delay. Why does the current programme not show this delay?

    So what should tbe the PCD/CD dates if original PCD = CD = 13/08/12.

  5. 0
    Gary Whitehead ·

    Emmaunelle,   You say there

    Emmaunelle,

     

    You say there is a delay, but you also say that the current programme doesn't show the delay -please explain

  6. 0
    Ahmed KHR ·

    I think there is some

    I think there is some constraint on the Critical path (Madatory finish for exemple) this why you don't see this delay on the end or the delay is on an activities wich have more than three weeks float.

     

    You should chek your activities wiche have contraints first (make it free), chek the activities TF...

     

    Regards.

    Ahmed

  7. 0
    Emmanuelle Prefol ·

    Think I might have

    Think I might have overcomplicated the issue. So I should try to simplify:

    1 - Can the PCD be after the CD further to for instance contractor's caused delay?

    2-  Can the PCD ever be brought back to be before the CD?

     

     

     

     

  8. 0
    Anoon Iimos ·

    1. Yes - can be due to any

    1. Yes - can be due to any delay;

    2. Yes - by crashing your schedule, adding resources or whatever

    you can also see delays if you got negative floats