ERROR MESSAGE SLDNA-0655-B CANNOT COPY ANY ACTIVITIES- SUGGESTED HELP PLEASE?

Tom GouldburnMember for 14 years 1 month
Created
3
4
0

HI Guys,

 

I'm pretty new to the p6 Program and I'm only just starting out as a Junior project planner. On my second week now and I've all ready managed to currupt the program...lol :-(

 

When copying and pasting an Activity with relationships I seem to be getting an SLDNA-0655-B error message. Obviosuly I've exited the program and restarted it, however the problem still seems to be there.

 

SCREEN SHOT BELOW.

 

 

 

If any of you technical experts can offer any help, would be more than  appreciated.

 

Cheers,

Tom

3 replies

Oldest first
  1. 0
    admin ·

    Hi Tom,Fromwhat we

    Hi Tom,

    Fromwhat we understand, this is a documented bug on P6 v7.  You have to do is to download and install Primavera SP2 (service pack 2).  You will have to go to the Oracle support site and download the patch it is 130 MB.

    Hope this helps?

    PP Team

  2. 0
    Mostafa Hassanein ·

    I have same problem but only

    I have same problem but only in one project of my multy projects data base Oracle Premavera P6 ver 7.

     

  3. 0
    Zoltan Palffy ·

    is it possible that you have

    is it possible that you have two projects open with the same activity numbers ?

    look at the very top there should only be one project named with no comas after the project name