program links

Nader SallamMember for 16 years 11 months
Created
1
4
0

why allways the client is not satisfied with program links.the links between activities ,shop drawins and coordination drwings the program become complicated for MEP activities and civil can any body help me with his experience

1 reply

Oldest first
  1. 0
    Ashraf Alawady ·

    Hi,to my knowledge , the

    Hi,

    to my knowledge , the links beween the activities has specific logic and sequace based on the method of construction , for example the activity can not be statred without approving the related detailed shop drawings, obtaining No Objection certificates from the cocerned authorities, approval of the materials ,approval of the method statment, have the required resources and finish all the predessor activities which have the relation finish to start with this activity.

     

    the client has to chech the sequance and logic and if it is complining with the normal construction sequance and logic then they have no wright to object in this issue other with the program will be meaninglesss.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?