Filter is not working properly???

Chris G.Member for 20 years 3 months
Created
8
5
0

Dear Experts,

Good day! I know this question is supposed to be a no brainer, however, when I try to filter using the "WBS NAME; contain = Electrical" to show all the activities under Electrical from multiple buildings unfortunately most of them doesn't show up. I tried to copy the WBS name of the one showing up and apply to the rest but still not working.

Does anyone encounter already this issue on P6 v8.1?

Your assistance is highly appreciated.

regards,

Chris

8 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Chris Are you applying the

    Hi Chris

    Are you applying the filter to the whole project?

    Best regards

    Mike Testro

  2. 0
    Dieter Wambach ·

    Hi Chrisuse "WBS" then "is

    Hi Chris

    use "WBS" then "is under". Then you can select "electrical".

    Pay attention for other active filters.

    Good luck!

    Dieter

  3. 0
    Raymund de Laza ·

    Chris, I suggest to create

    Chris,

    I suggest to create Activiy Code to make the filtering easier.

  4. 0
    Chris G. ·

    Mike, Yes I was trying to

    Mike, Yes I was trying to apply for the whole project that consist of several buildings with the same WBS structure.

    Dieter, I guess using the "under" will be too much of a parameter since I am trying to filter for multiple buildings.

    Raymund, I think I dont have much time to create and code each activities, and at this tender stage.

     

    I really dont know whats wrong, even I try to re-type one WBS name to refresh. For now, I am just using a combination of activity names and activity ID's to filter since I create them as typical.

    BAFINxxx = Finishing Activites for Building A

    BBFINxxx = Finishing Activites for Building B

    BAELExxx = Electrical Activities for Building A

    BBELExxx = Electrical Activities for Building B

  5. 0
    Dieter Wambach ·

    Hi ChrisThe filter under

    Hi Chris

    The filter under shows you all activities under WBS e.g. "Electrical". That's the way I understood your question

     

    Dieter

  6. 0
    Gary Whitehead ·

    Chris,   Try Dieter's

    Chris,

     

    Try Dieter's suggestion. I believe it is the correct solution for you.

     

    Cheers,

     

    G

  7. 0
    Raymund de Laza ·

    What I understand from Chris

    What I understand from Chris requirement is that He want to filter out only Electrical Items from different Facilities in the same Schedule.

    01 Main Building:
       01.01 Electrical Works
           01.01.01 Power Sys

    02 Generator Building:
       02.01 Electrical Works
            01.01.01 Power Sys

    03 Guard House:
      03.01 Electrical Works
          01.01.01 Power Sys

    and so on.

     

    In doing so... Filter

    1. WBS under = 01.01
        WBS under = 02.01
        WBS under = 03.01

    2. Create Activty code "Electrical"
        Activity Code = Electrical

     


       

  8. 0
    Chris G. ·

    Thanks for all of your tips

    Thanks for all of your tips guys...

    Ciao,
    Chris