Loading and Welding Sequence of Pipes on Racks
- Created
- 8
- 4
Hi All Welding Experts
I am putting together a baseline programme for a large industrial plant where the pipeline contractor is telling me that his planned sequence of work for each section of piperack was:
Start loading out prefab pipes - biggest / heaviiest on high racks then smaller / lighter on the low racks.
Welding then starts on the high rack pipes while loading out is going on below.
I have my doubts about this sequence on two of fronts:
1. Health and Safety Rules with welding overhead of loading out.
2. Practicality of welding round a small pipe with a large pipe above it - on average there is 100mm lagging so max 300 gap.
Please give me the benefit of your experience on these matters.
Best regards
Mike Testro
8 replies