Differences between using FS or SS Relations With Milestones Activities ??

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
3
2
0

Dear Freinds;

Are there any differences between using FS or SS relations with Milestones activities ?

 
Please Advise

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Yaser A SS Link will start

    Hi Yaser

    A SS Link will start at the start of the predecessor task and a FS will link come from the end of the predecessor.

    In Asta PowerProject a FS/SS link will take on the calendar of the predecessor but a FF link will use the successor calendar.

    Best regards

    Mike Testro

  2. 0
    Yaser A. Al-Bustanji ·

    Thanks but my question about

    Thanks but my question about the effect of this relations when the predecessors is milestone (Zero Duration) in p3 or 

  3. 0
    Mike Testro ·

    Hi Yaser Linking from a

    Hi Yaser

    Linking from a milestone the same calendar rules apply - otherwise the is no difference.

    Best regards

    Mike Testro