Data Date Time
In the Open Standard
Mike TestroMember for 20 years 10 months
- Created
- 2
- 3
0
Hi All
I was reviweing a contractor's schedule as part of a delay analysis exercise when I noticed that the time set on the data date progress line was 08:00.
The work calendar is due to start on 07:00 so for every progress report one hour is lost on the programme.
It could have been much worse if the data date time was 12:00.
I suggest that the time on the data date is set earlier than the dominant work patter start time.
Best regards
Mike Testro