SPI & CPI in P6 monthwise

Zil-e-Subhan MalikMember for 15 years 7 months
Created
2
3
0

Dear All,

 

WE know that SPI and CPI are calculated by p6 and we only need to open the columns to see the values.

I want to know, is it possible in P6 to have a month wise SPI & CPI from the start of the project to the current date. If it is possible please tell me how?

Regards,

 

Malik

2 replies

Oldest first
  1. 0
    Rob O ·

    How do I set up a schedule so

    How do I set up a schedule so that it calculates SPI correctly? What % complete types, settings, etc?

  2. 0
    Zoltan Palffy ·

    what if you grouped by Start

    what if you grouped by Start then make the Interval Month  ?