Incorporating A new Time Schedule to your old one

Javad MaroufMember for 13 years 4 months
Created
2
2
0

I have this problem at work: I have my time schedule which is updated up to data date, now a new area is going to be added to project scope which the engineering and construction activities have been started 2 months before. now thay ask me to prepare a time schedule for this new work and incorporate it to my plan. please guide me in this regard how can I attach this new schedule to the project schedule(considering that some activitie in both are done or progressed) next how shoud I incorporate this change to the baseline?

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi JavadSave the old

    Hi Javad

    Save the old programme in a new file and then just build up the new programme as if it was a sub-project.

    Place the necessary logic to the old programme tasks and the enter progress.

    Best regards

    Mike Testro

  2. 0
    Vladimir Liberzon ·

    Javad,it depends on the

    Javad,

    it depends on the software that you use.

    In Spider Project you just create the schedule for the new area and select Add project as new phase in the project pop-up menu. Then select your project for new area and that's all.

    The same may be done with the baseline where you may add initial subproject schedule where actual data was not entered.