Adding Indirect Cost Through Primavera

Ammar TauqeerMember for 13 years
Created
2
4
0

I've recently started Working as a Planning Engineer and I am currently working on a project for which I have done Scheduling, Resource Scheduling and Costing for that Project But I am stuck in one thing that is our work is done in remote areas and we provide facilities to our manpower like Transportation allowances,Food Allowances,Daily transportation From camp to Site, accommodation.I want to add there costs in my project and show them Separately. Any Suggestions Would be appreciated.

2 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi AmmarI suggest to use the

    Hi Ammar

    I suggest to use the "expenses" facility and enter these in a WBS summary at the location you see the most fit.

    Regards Johannes

  2. 0
    Ammar Tauqeer ·

    Thanks Johannes Really

    Thanks Johannes Really Appreciate it .

     

    Regards,

    Ammar Tauqeer