Skip to content

Graph

Ammar TauqeerMember for 13 years
Created
6
3
0

Dear All,

I want to have a graph between how much Perfomance% has been completed with respect to schedule %(of the whole Project).

6 replies

Oldest first
  1. 0
    Ammar Tauqeer ·

    Or you can say i want to

    Or you can say i want to track my project graphicaly 

  2. 0
    Raymund de Laza ·

    Show the Planned Value Cost

    Show the Planned Value Cost and Earned Value Cost Curves.

  3. 0
    Ammar Tauqeer ·

    Told them to do so but they

    Told them to do so but they want progress in terms of duration.

    How much performance % is completed of Planned %

  4. 0
    Mike Testro ·

    Hi AmmarThis kind of data is

    Hi Ammar

    This kind of data is best generated on an Excell Graph.

    Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.

    Keep the graph format for the next progress update.

    Best regards

    Mike Testro

  5. 0
    Ammar Tauqeer ·

    Thanks Mike.I want to show

    Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)

  6. 0
    Ammar Tauqeer ·

    I can only enter schedule %

    I can only enter schedule % complete data upto current data date.But i want to have schedule % complete of the whole project before hand.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?