I am trying ti establish a filter for hiding the activities in a schedule that are 100%.

That is easy.

My schedule is broken down by 4 areas.

As part of that filter, I still need to show all activities (including the ones that are 100% complete) in 1 of those areas.

(so basically I want to show all activities that are not complete, but I also want to show all activities (complete or not) in one of the 4 areas.

 

All activities are task dependent.

Thanks,

Chris

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi ChrisCreate a code for

    Hi Chris

    Create a code for each of the areas - Area 1 - Area 2 etc.

    Assign the relevant code to every task in the respective area - then filter accordingly - Complete & Area.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    Chris,Terminology may vary

    Chris,

    Terminology may vary depending on which software you are using, but filter on:

     

    Area = Area 1

    OR

    Percent complete does not equal 100

     

    Cheers,

     

    G