Cost Allocation
In the Open Standard
Robert CorranMember for 22 years 10 months
- Created
- 2
- 3
0
Hi Eveyone
Can someone please help me, I assigned costs to a programme which basically is to sit back to back with an estimate. The prgramme consists of 5 LoE activities running from 02 Jan 2014 to 31 March 2014. However when I produced the stacked histogram and cost report it had apportioned some cost to December 2013; Why is my question. Also the costs have been allocated to the Monday of each week instead of being spread linearly any advice would be greatly appreciated.
Thank You
Rob Corran