PRIMAVERA v6.7 Completing Tasks When Performing Updates with Data Line
In the Open Standard
Charlie DanielsMember for 12 years 10 months
- Created
- 2
- 4
0
Hi,
I have been experiencing this problem for a while now and have not found the solution.
When I perform the updates to the schedule:
Select New "Data Date", and then Apply
Some activities that should still be in progress seems to have been completed automatically.
And it is completed on a past date.
This is a big problem as I have to go and check all the activities after the update and when busy with a large program this is not very good for business.
Does anyone have this problem, do you have a solution?
Thank you
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?