Skip to content

Successors calapse when manually starting or completing a predecessor

Charlie DanielsMember for 12 years 10 months
Created
5
3
0

Hi,

 

When I manually tick the start option of a task and then hit shedule, the successors will fall back to the data line.

 

The same thing happens when I Manually complete a task the successors will fall back to the dataline.

 

Is there anyone with a solution to this problem?

 

Thanks

 

P.S. Manually complete or start meaning not with the datadate update.

5 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Are the actual start/end

    Are the actual start/end dates you are manually entering earlier or later than the data date?

     

    When you say "fall back" to the data line, do you mean the successors become later than they were showing before you scheduled, or earlier?

  2. 0
    Anas Nasr ·

    You are probably suing

    You are probably suing progress override option in the advinced schedule options menu. Change this option to retained logic and successors will not fall back on the data date.

  3. 0
    Charlie Daniels ·

    HI Anas"You are probably

    HI Anas

    "You are probably suing progress override option in the advinced schedule options menu. Change this option to retained logic and successors will not fall back on the data date."

     

    Where do I find this option, I am using P6.7?

     

    Thanks

  4. 0
    Sendhil Kumar ·

    Hit F9 --> Options -->

    Hit F9 --> Options --> "General" tab --> check retain logic option.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?