hey all ,, I've start my new jop as a planner engineer, i want to konw how to set the update Options in the P6 because i think that there is a problem ,, when i update an activity that isn't finish yet, by mark it as started and insert a percentage of complete the float jumb to be very larg !!,,so i realy need to know how can i go to the options of the update and try to solve this problem ,,

 

  Thanks,,

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Sounds more like a problem

    Sounds more like a problem with the logic than the update options to me.

     

    What successor relationhsips does the activity in question have? (finish to start, start to start, etc)

  2. 0
    Osama Haggag ·

    Its Finsih to start

    Its Finsih to start relationships,,more than one activity ..