Update OPtions
In the Open Standard
Osama HaggagMember for 12 years 8 months
- Created
- 2
- 3
0
hey all ,, I've start my new jop as a planner engineer, i want to konw how to set the update Options in the P6 because i think that there is a problem ,, when i update an activity that isn't finish yet, by mark it as started and insert a percentage of complete the float jumb to be very larg !!,,so i realy need to know how can i go to the options of the update and try to solve this problem ,,
Thanks,,
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?