Skip to content

Adtivity Duration and resource levelling

Nikan GMember for 12 years 9 months
Created
5
3
0

hi people,

I am new in planning, and It would be highly appreciated to answer my BASIC questions :)

  • Have an activity which actually takes 12 hours but in 2 weeks, how I can plan it? already in my schedule,  it started on 17th Feb and will finish 28th Feb., which is 80 hours for duration that is not correct, what is planning solution for this?
  • the resource who is working on above job, is working on other four tasks as well. During in 2 weeks he is working 12 hours to finish mentioned job and other 4 tasks which not finish in 2 weeks. how I can show his work hours in my plan?
  • Last question: why finding is not working most of the time? To search an activity ID I use find but doesn’t work! I Mean I can find manually but in finding window it says no result!

 

Thanks in advance guys!

Nikan.

5 replies

Oldest first
  1. 0
    Gary Whitehead ·

    What software are you using?

    What software are you using?

  2. 0
    Mike Testro ·

    Hi NikanSet up a work pattern

    Hi Nikan

    Set up a work pattern for 6 hours a week - say 1 hour per 6 day week - then apply this to a calendar - then apply the calendar to the tasks.

    Best regards

    Mike Testro

  3. 0
    Vladimir Liberzon ·

    12 hours in two weeks means

    12 hours in two weeks means 12/80*100% = 15% workload.

    At other tasks calculate resource workload and if their sum does not exceed 85% then these jobs may be done in parallel.

    Another way is to use variable resource assignments but in Spider Project only.

    Please specify the software that you use to get specific advise.

  4. 0
    Nikan G ·

    Primavera! P6.7

    Primavera! P6.7

  5. 0
    Nikan G ·

    Primavera! P6.7

    Primavera! P6.7

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?