Manhours as resource
- Created
- 7
- 5
Hi,
We have a sub-con who has loaded Manhours as a resource for all the Disciplines and related activities. As per contract client has specified that 260mhrs/month need to be considered as basis for planning. On this basis they have extracted from P6 manhours budgeted per month divided by 260 manhours to get the manpower required for the month. But they are activities where the resource utilization is only .35days and so. please refer the link. Should i agree with them or go to each activty get the activity duration based on the calender and then divide the manhours-budgeted by the duration to get the manpower requirements.
Kindly guide me.
https://app.box.com/s/ew5xqzt5sgm4qsul27p1
Br-
rajkamal
7 replies
Oldest firstLog in or join to reply