Activity % Complete in Totals and Sub-totals do not appear

Arvin PuraMember for 12 years 7 months
Created
6
2
0

Hi Planning Experts,

Currently I am updating my programme in P6. My programme is resource loaded with manpower and material. In updating I am using Activity % complete in the column and physical % as the percent type. But after updating there I cannot see the % complete in the total and subtotals (or wbs bars). Need help and advise.

 

Thank you.

Arvin

6 replies

Oldest first
  1. 0
    Gary Whitehead ·

    1) Admin > Admin preferences

    1) Admin > Admin preferences > Earned Value. Ensure "techique for calculating performance % complete" is selected as "activty % complete"

    2) Display the column "performance % complete". This will show in totals.

     

    Cheers,


    G

  2. 0
    Arvin Pura ·

    Hi Gary,thanks.Arvin

    Hi Gary,

    thanks.

    Arvin

  3. 0
    Arvin Pura ·

    Hi Gary,I do the steps you

    Hi Gary,

    I do the steps you advised. Still it did not show.

    Thanks.

    Arvin

  4. 0
    Kannan CP ·

    Hi Arvin,Activity percent

    Hi Arvin,

    Activity percent complete will not roll up (summary%) to WBS level, only for each activities.

     

    kannan

  5. 0
    Gary Whitehead ·

    Arvin, It works for me, so

    Arvin,

     

    It works for me, so not sure what to advise. -Have you baselined?

  6. 0
    Rangarajan Ramaswamy ·

    Hey Arvin , i got your

    Hey Arvin , i got your problem. Understand one thing P6 never shows summary % complete in Activity % column. Chew on it. To know % progress at summary level you have to add Performance % Complete column.

    Now switch to P6 and do that first before you continue.

     

    Voila!! there you go, now you can see the % complete and can thank me for that.

     

    However if P6 still doesnt show the % complete at sumary level follow the below steps.

    I want you to check if you have assigned cost for your resources.

    If not, P6 is not going to give you a damn % complete on Summary level.

    So you have two options:-

    1. If you do not want your schedule to be cost loaded, just put resource Price/unit as 1/unit. Recalculate assignment cost. This will get you going. Or

    2. Load the actual cost of resources and materials, you have the % complete in summary bars.

    I hope this solves your problem.

    Regards,

    Ranga