Activity % Complete in Totals and Sub-totals do not appear
In the Open Standard
Arvin PuraMember for 12 years 7 months
- Created
- 6
- 2
0
Hi Planning Experts,
Currently I am updating my programme in P6. My programme is resource loaded with manpower and material. In updating I am using Activity % complete in the column and physical % as the percent type. But after updating there I cannot see the % complete in the total and subtotals (or wbs bars). Need help and advise.
Thank you.
Arvin
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?