How to Rearrange Activity ID's in an Ascending Order in Primavera P6 V6,

Royce David SacdalanMember for 12 years 6 months
Created
1
4
0

its like im having an existing schedule then ive decided to add more activities and rearrange the sequence...unfortunately the Acitivity IDs were no longer arrange in an ascending order, since i already change the sequence, how can i rearrange them in an ascending order again? lets say ive got a total of less than 1500 activities.

1 reply

Oldest first
  1. 0
    Jose Frade ·

    You can use several methods.

    You can use several methods. in V6 you can use Global Change / Excel

    1. create a user field

    2. Export to Excel and populate the user field with the Act.ID you want and import back

    3. Create a global change to repalce Act ID with value from User field

    BR

    JMFrade

     