concrete tracking reports

Haytham SaadMember for 13 years 6 months
Created
1
4
0

I am working in a project contains 3 main concrete buildings A & B & C  each has its total concrete Quantity, i was asked to produce a report showning the excuted Quantities vs  Planned Quantities and showning remaining Quantities, also showning the productivity required to maintain finish date for each building an over come the delay , my question is what should the report contain and if there is any form for these reports, thnxx

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi HaythamSet up a

    Hi Haytham

    Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect.

    This will give you the total m3 of concrete in the project.

    Put a date column in the spreadsheet.

    Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item.

    You can then keep a running total of actual concrete production to compare with your planned production rate.

    Best regards

    Mike Testro

     