concrete tracking reports
In the Open Standard
Haytham SaadMember for 13 years 6 months
- Created
- 1
- 4
0
I am working in a project contains 3 main concrete buildings A & B & C each has its total concrete Quantity, i was asked to produce a report showning the excuted Quantities vs Planned Quantities and showning remaining Quantities, also showning the productivity required to maintain finish date for each building an over come the delay , my question is what should the report contain and if there is any form for these reports, thnxx
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?