Updating Multiple Resource Loaded Activities
In the Open Standard
Katie CoombsMember for 13 years 3 months
- Created
- 0
- 2
0
Hello,
I am updating a project that has activities with multiple resource assigned to them. However, when I update the activity with a new percent complete and actual hours - it does apply the same percent complete to indiviual resources and the actual units does not distribute evenly. Rigt now I have to go into the Resource assignments tab and update indivual resources instead of activities.
Right now am using Fixed Units as my duration type & units percent complete.
Any help would be greatly appreciated.
Kaitlin