Skip to content

Updating Multiple Resource Loaded Activities

Katie CoombsMember for 13 years 3 months
Created
0
2
0

Hello,

I am updating a project that has activities with multiple resource assigned to them.  However, when I update the activity with a new percent complete and actual hours - it does apply the same percent complete to indiviual resources and the actual units does not distribute evenly.  Rigt now I have to go into the Resource assignments tab and update indivual resources instead of activities.

 

Right now  am using Fixed Units as my duration type & units percent complete.

 

Any help would be greatly appreciated.

Kaitlin

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?