WBS & activities percentage refelection issue

Rana Muhammad ShoaibMember for 12 years 7 months
Created
1
2
0

i prepared plan. later on i added few WBS along with activities. when i updated plan i am facing following problem.

The activities are showing performance and schedule percentages where as newly added WBS are not showing percentages.

Kindly guide me to rectify this error.

1 reply

Oldest first
  1. 0
    Jerome Odeh ·

    Your schedule needs to be

    Your schedule needs to be cost loaded for progress to roll-up to WBS level.

    Assign cost to the new activities and their WBS will display performance & schedule % completes.