This may apply to Column and Suspended Slab with Activities description as Columns & Suspended Slab.
Say Suspended Slab @ EL=+4.00 was casted yesterday, the columns @ EL=+4.00 and suspended slab @ EL=8.00 activities can now be started. The Activities for Forwmworks for Suspended Slab @ EL=8.00 may wait for some Columns to be started in order to commence but the Suspended Slab @ EL=8.00 can never be completed unless all Columns are completed.
Susp Slab SS+3d with columns
Slab FF+6d with columns
Although in some cases Suspended Slab may not need to wait for some columns to be started becasue Scaffoldings used for the safety purposes in casting of columns will be retained to be used for the slab formworks. Therefore Suspended Slab activities can start once predecessor slab already casted.
For Activites with a deeper details such as Formworks for Columns @ Grid 1 & 2, Grid A-M, Rebars for Columns @ Grid 1 & 2, Grid A-M, Laying of Scaffolding along Grid 1 & 2, Grid A-M, Casting of Concrete for Columns @ Grid 1 and so on.... the required Link is only FS.