Reporting multiple critical.paths

Gary EdwardsMember for 12 years 3 months
Created
2
2
0
Good morning all, I have been a planner for about 18 months now and for the first time I have been asked by the SPM to produce a report showing the first five critical paths. How do I get P6 to display this? Is this best presented as a programme with multiple, different coloured paths or is there a reporting template which I can go on to update each quarter? Thank you. Gary

2 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Gary First you must P6 let

    Hi Gary

    First you must P6 let calculate them: F9 --> "Options" --> "Advanced" --> mark it plus the number you want.

    Then you can group and filter by the paths and give them different colours in the bar chart.

    Good luck with your planning!

    Dieter

  2. 0
    Gary Edwards ·

    Thank you very much Dieter.

    Thank you very much Dieter.

Log in or join to reply