Dear All,

During govt holidays client annonced site non working for another 9 days , in this case other than calendar break hours

any other methods to evaluate the delay . Your valuable comments will be highly appreciated.

Regards,

S.Babu.

8 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi SunilAny stoppage is

    Hi Sunil

    Any stoppage is bestdisplayed on the calendar.

    Best regards

    Mike Testro

  2. 0
    Sunil Babu ·

    Hi Mike,Thanks for your

    Hi Mike,

    Thanks for your reply. Already made the calendar adjustments, out of 12 days 9 days sttoppage by client.

    3 days govt holidays . In delay analysis how will it reflect .

  3. 0
    Kannan CP ·

    Hi Sunil,Update your schedule

    Hi Sunil,

    Update your schedule just before the commencement of 9 days holidays declared by client. Keep a copy of it, with the calendar showing the 9 days as normal days.

    In the next step, change the calendar for the said 9 days (as holidays). Schedule it (F9). See the difference.

    May be you will work couple of days in the said 9 days, but still as per SCL, IN MY UNDERSTANDING, you are entitled for an extension of 9 days(due to the disruption from Client side).

    Comments are welcome.

    Regards

    Kannan

  4. 0
    Sunil Babu ·

    Hi Kannan,I applied the same

    Hi Kannan,

    I applied the same logic, only thing I want to segregate the delay part of the project caused by the disruption from the client side

    Thanks

    Sunil.

  5. 0
    Kannan CP ·

    Hi Sunil,Update your schedule

    Hi Sunil,

    Update your schedule just before the commencement of 9 days holidays declared by client. Keep a copy of it, with the calendar showing the 9 days as normal days.

    In the next step, change the calendar for the said 9 days (as holidays). Schedule it (F9). See the difference.

    May be you will work couple of days in the said 9 days, but still as per SCL, IN MY UNDERSTANDING, you are entitled for an extension of 9 days(due to the disruption from Client side).

    Comments are welcome.

    Regards

    Kannan

  6. 0
    Kannan CP ·

    Hi Sunil,It depends on the

    Hi Sunil,

    It depends on the status of the project before the commencement of the 9 days holidays. May be you are already in delay by that time.

    If there is no delay in your part, show to client the updated schedule indicating the 9 days of extension from the Contract completion date. If there is delay from your part (for eg: 30 days), still you will get 9 days EOT, for the rest you are responsible.

     

    Kannan

  7. 0
    Syed Hussain ·

    Sunil, You will only be

    Sunil,

    You will only be entitled to extension if delayed task is on critical path i.e. delay is not being absorbed by available float. If flaot available is 4 days then you will get only 5 days extensions as in this case completion date/deliverable is being dalayed by 5 days only.

     

    Syed

  8. 0
    Sunil Babu ·

    Hussain,It is quite apparent

    Hussain,

    It is quite apparent that as many days I am getting delay, I can avail that.

    Ony thing that before schedule with holiday period we should make sure

    that there is some delay or not, and after schedule how it was affected.

    Regards,

    Sunil.

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?