Milestone Duration

Paul ZachariaMember for 12 years 3 months
Created
1
2
0

Could you please explain how to add duration to a start or finish milestone.. It's getting changed to the data date everytime I schedule it.. I am using P6 v 8.3

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi PaulWelcome to Planning

    Hi Paul

    Welcome to Planning Planet.

    By definition a milestone has zero duration.

    If you add a duration it becomes a task.

    Best regards

    Mike Testro.