Skip to content

Engineering / document approvals in Primavera P6

Haroon RasheedMember for 18 years
Created
6
3
0

Hello,

I am creating a new schedule and want to understand best practices by experts here.

How are you managing engineering or document approvals in your schedule?

  1. Submission/Approval - as a single activity?
  2. Submission linked to approvals - as separate activities?
  3. Or you manage it in a separate software and update percentages only to WBS summaries?

Thanks in advance,

Haroon

6 replies

Oldest first
  1. 0
    Kannan CP ·

    Haroon, Always divide the

    Haroon,

     

    Always divide the engineering document submission in to 3 section

     

    1. Submission duration

    2. Review/Approval duration as per the contract(may be approved or to resubmit or approved as noted)

    3.Follow up and final approval (consider 2-3 revision durations)

     

    Procument may start after no.2 (may be it is approved as noted) but the manufacturing you cant finish without the final approval.

    For construction related design, you should get the final approval no.3 prior to any works (otherwise you can start in your own risk)

    Regards

    Kannan

  2. 0
    Mike Testro ·

    Hi KannanYou are absolutely

    Hi Kannan

    You are absolutely correct but there are some further refinements that I would suggest.

    The design and approvement cascade should be set up for each work package and linked to start of the package work.

    The cascade should be as you suggest Design Approval + Order + Work Design + Procurement + Delivery + Port Clearance + Stock on Site.

    This simple cascade should be set ALAP when linked to the work package Start Work Milestone.

    Best regards

    Mike Testro

  3. 0
    Haroon Rasheed ·

    Thank you for the clarity -

    Thank you for the clarity - @kannan & @Mike.

    -Haroon

  4. 0
    Haroon Rasheed ·

    Thank you for the clarity -

    Thank you for the clarity - @kannan & @Mike.

    -Haroon

  5. 0
    Haroon Rasheed ·

    Thank you for the clarity -

    Thank you for the clarity - @kannan & @Mike.

    -Haroon

  6. 0
    Kannan CP ·

    Hi Mike,I agree with you that

    Hi Mike,

    I agree with you that the submission/approval should be done for each WP.

    Best Regards

    Kannan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?