S Curve re-baseline retrospective comparison
- Created
- 0
- 3
Dear All,
I have re-baselined a percentage complete (earned Man-hour value / budgeted Manhour value) v/s. Time S - Curve at 75% project completion.
Subsequently I have been asked to determine Retrospectively , what was the earned value % when the project was at 50% completion. In such a case should the earned value % be
a) Actual earned value % (say 45% at 50% completion) because the rebaselining had been done AFTER 50% milestone had been completed OR
b) Earned Value % shall be equal to 50% at 50% completion because the S - Curve has been re-baselined.
I am aware that Rebaseline affects the forecast / 'To go' part of the S - Curve with the Actual % = Planned % ON the date of the rebaseline. But what about the PAST Actual percentages , do they also become Actual % = Planned % on re-baselining ?
Kindly let me have your opinion.
SH
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?