P6 Keypoint
In the Open Standard
Tunji AdewaleMember for 12 years 3 months
- Created
- 7
- 3
0
Dear All,
NOTE: I assumed that am working as a planner of main contractor
1. Can you pls explain to me how I can update my activity progress on P6 assuming am
working with main contractors and sub contractors want to update me?
2. if am working wt main contractor and sub contractors are using excel, how will they update me
their progress report and how will I add the update manually from my own?
3. is it possible to automate schedule excel sheet from sub contractors to my own primavera instead
of updating one after the other?
4. If am working as a planner of main contractor, who will update to me an activity progress report, is it planner of sub contractor or our own activity manager or WBS responsible manager?
5. Let take for example I have one particular activity on my P6 and this same activity is broken to 6 different activities on sub contractor level, Does that means that I will use STEP to include all these?
6 activities under that activities and continue to update it one and after the other? who should be my first point of contact in updating progress report, is it activity progress reporter of main contractor or planner of sub contractor?
7. what are my responsibilities as a planner in ensuring that shop drawing, material submitter, material approval, material procurement and material delivery to site. is it that i will be sending emails to all them to remind them or what will I do in carrying out my responsibilities in all these WBS?
8. Do I need to have my excel sheet to track shop drawing, material submitter, material approval, material procurement and material delivery to site progress or I can be going to Document Controller and Procurement Manager for this?
9. If client or Consultant needs an update from me, will they tell me the field like start, finish, BL1 start, BL1 finish, activity % and so on to be included in the report?
10. what are my daily responsibilities as a Planner working wt Main Contractor?
11. who will provide me with list of activity to be included in p6, are they site engineers, civil engineers, MEP engineers, architect, and so on?
12. Which is the best among Physical, Duration and Unit to update activity?
13. Can I say materials submission, material approval, material procurement and material delivery to site belongs to level of effort activity type or which?
NOTE: Pls mention the number when you are responding.
Best Regards,
Yakubu
7 replies
Oldest firstLog in or join to reply