Critical Activity
In the Open Standard
oyewole waheed BabatundeMember for 12 years 2 months
- Created
- 5
- 1
0
Hi All,
I made a schedule of about 99 activities and after running my F9 (schedule), I found out that all my activities have
negative total float and turned every activities to be critical because I set my critical to "Total Float equals or less than 0hr" but when I changed to "Longest Path", then I have like 70 critical activities.
My question goes like this: Is this normal? If not what do I need to do.