Skip to content

Activity % Complete

Tunji AdewaleMember for 12 years 3 months
Created
2
4
0

Hi Members,

Can anybody help me with updating activity % complete from importing excel file. I am currently facing issues in this. I can and have been able to export my p6 file to excel, update and re-import and its all working fine for BudgetedTotal Cost, Budgeted Unit, Duration and so on. But for Activity % Complete, it is not working?

 

Pls Help

2 replies

Oldest first
  1. 0
    Jerome Odeh ·

    Hi Yakubu,You also need to

    Hi Yakubu,

    You also need to update Actual Start Date for the updated Activity % Complete to be reflected.

     

    =jerome

  2. 0
    Dieter Wambach ·

    Hi Yakubu There are two

    Hi Yakubu

    There are two conditions to maintain this item manually:

    1. The activity must be started, as Jerome wrote

    2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?