Skip to content

Resource Finish Dates Differs on Activity finish Dates

Cecil SolivaMember for 22 years 6 months
Created
4
3
0

Dear Planners,

I got encounter this kind of problem when I undergone a recovery plan to my project, of which after finalizing the schedule I exported the resources to get the resource planned based on the activity loading. I found out that the dates are not matching with the activity dates. May i lend your ideas how to manipulate this error.

 

Thank you,

 

cecil

4 replies

Oldest first
  1. 0
    Gary Whitehead ·

    It may be that your resource

    It may be that your resource calendars are different to your activity calendars

     

    It would help to know what software you are using, though.

  2. 0
    Cecil Soliva ·

    Hi Guys, Thanks for your

    Hi Guys,

     

    Thanks for your ideas, but I used the same calendar for the activities and resources. P6. V.07 am using..

  3. 0
    Raymund de Laza ·

    Cecil,I experienced the same

    Cecil,

    I experienced the same and my workaround is Remove the Resources and reassign again. It may occur in a few resources though.

     

    Regards,

  4. 0
    Rafael Davila ·

    Deleted by Rafael Davila as

    Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

    So old no longer Photobucket pictures aer available.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?