Sequence of Construction Activities ( Planning )

Question AnswerMember for 12 years 7 months
Created
3
2
0

Hi Everyone

 

I'm trying to create a Programme of works for a commercial building and i really need a guidance on the sequence of works that'll probably state the activities that needs to follow each other both Civil,MEP/Architectural. Either a book or a Link to a Video will be appreciated. I just want to have ideas of creating the right relationship for the right activities ( in General )

regards

 

Questionier

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    site

    site work

    foundations

    superstrucutre

    skin

    equipment 

    finishes

    fit-out 

  2. 0
    Mike Testro ·

    Plus Test & Commission

    Plus Test & Commission

  3. 0
    Zoltan Palffy ·

    oopsyes Mike i forgot that

    oops

    yes Mike i forgot that important one thanks 