Reviewing progressed activities
In the Open Standard
Folahan AdebayoMember for 12 years 3 months
- Created
- 5
- 3
0
Hi all,
Can you suggest an easy way to review the progressed activities from contractor's updated program? I mean how can I simply filter all activities that was progressed within the week (reporting period) without having to scroll through thousands of activities to find the changes in Performance % btw this period and the last period. Preferably another approach besides the Claim Digger (To me...thats not so cool).
Thanks
Idris.
5 replies
Oldest firstLog in or join to reply