Loaded Costs are not spreading in the activity's duration

Celso PamanMember for 16 years 9 months
Created
4
3
0

Dear Experts,

We have a program fully loaded with cost and manpower. The problem that we are facing right now is that lots of costs that were loaded to the program are not spreading to the entire duration of the activity. 

Can anyone share his knowledge on resolving this issue?

 

Thanks in advance.

Celso

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    make sure that your resource

    make sure that your resource is using the same calendar as your activity. 

  2. 0
    Celso Paman ·

    Yes. they have the same

    Yes. they have the same calendar.

  3. 0
    Zoltan Palffy ·

    on the left try changing the

    on the left try changing the column to early start and early finish instead of just start and just finish

    check to see if the Drive Activity Dates by default option has been switched off. Make sure that the calendars match down to the exact workhours, because even if a resource assignment is ending on the same day as the activity, if they are out of sync by even 1 hour, then the resource assignment will no longer sync up with the Activity's dates. Make sure you have your Duration Type set to Fixed Duration and Units/Time or Fixed Duration and Units.

  4. 0
    Celso Paman ·

    Thanks Zoltan.

    Thanks Zoltan.

Log in or join to reply