Hi All

I wish to see how much formwork decks are ín use' ie are keep in place while floors above are being constructed. What is the general rule here?

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    You must differntiate

    You must differntiate structure type, a post-tensioned structure is not the same as a flat slab or concrete joist slab.

    http://concreteconstruction.net/Images/Reshoring%20of%20Multistory%20Concrete%20Buildings_tcm45-340417.pdf

    http://www.concrete.org/Portals/0/Files/PDF/Previews/347205_2pager.pdf

    https://ardiansyahnegara.files.wordpress.com/2010/01/ch8_construction-loading-in-high-rise-buildings.pdf

    http://eprints.qut.edu.au/4051/1/4051_1.pdf