Help on P6 Remaining early start

Anthony ObasiMember for 11 years 4 months
Created
2
4
0

Hi all,

As I keep on thinking about P6 remaining early start description, I keep getting confused. The description says ' Remaining early start is basically the earliest date an activity in-progress can start or continue after the data date'. 

My question is why would an activity in-progress start or continue?  As it is already progressing why describe it as continuing?

Is this just a poor description? I will appreciate if somebody can throw more light on this.

 

Thank you.

 

Anthony

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    http://www.ronwinterconsultin

    http://www.ronwinterconsulting.com/Understanding_P6_Dates.pdf

    Go to article 3.5 page 12.

  2. 0
    Anthony Obasi ·

    Thanks Rafael

    Thanks Rafael