For the contruction planning what will be the right method on the manpower histogram.

Do i need to basing the unit man hour from the contract B.O.Q or from the manpower estimation on each activity.

Any advise please...

Regard's

Ron

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    If you have the manpower

    If you have the manpower estimate for each activity then you have the total is the Budgeted Quantity 