Calculation of budgeted units in prima vera
In the Open Standard
Ahmad uzairMember for 13 years 5 months
- Created
- 5
- 4
0
Hi all,
I have a building project in prima vera Orcale R8.1. I have resources of labour,Mason,Steel fixer.I know their average consumption per hour like for example,labour takes 3cft/hr for excavation.
My problem is that how do implement this data in my resources ? if my area to excavate is 500cft then my duration will be 20 days (8 hr/day). Now what will be my budgeted units and planned units in this
Please help me.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?


