Ordinal date

Ufuk KatirciMember for 10 years 10 months
Created
9
2
0

Hello everybody,

I am searching an answer for showing ordinal dates instead of ceartain dates but I couldn' t find a specific way. My problem is the project start date is not certain and I want to show the dates as ordinal dates, like to day 1, 2 etc instead of 25 dec, etc. 

At columns part I want to show ordinal date instead of BL project start - end.

I will appreciate if someone can help me,

Thanks & regards,

Ufuk

9 replies

Oldest first
  1. 0
    Amro Ahmed ·

    Hi,my suggestion to you to

    Hi,

    my suggestion to you to show in Gantt chart and just hide  colums of dates on activity table .

    Because in User Preference this not available option.

     

     

    Thanks

  2. 0
    Ufuk Katirci ·

    Amro thanks for your answer,

    Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess.  I can hide the dates columns but I have to show ordinal days ...

  3. 0
    Ufuk Katirci ·

    Amro thanks for your answer,

    Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess.  I can hide the dates columns but I have to show ordinal days ...

  4. 0
    Jerome Odeh ·

    Hi, Have you tried response

  5. 0
    Ufuk Katirci ·

    I have tried, I checked my

    I have tried, I checked my primavera but couldn' t see any "user_start_date1" or "user_integer1" etc. How can we create these.

    Thank you,

  6. 0
    Jerome Odeh ·

    Under Global Change, you

    Under Global Change, you should find these fields under the "Then" section parameter. See attached screenshots.

     

  7. 0
    Ufuk Katirci ·

    These data do not appear at

    These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...

  8. 0
    Ufuk Katirci ·

    These data do not appear at

    These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...

  9. 0
    Jerome Odeh ·

    Ufuk,Follow the steps

    Ufuk,

    Follow the steps below.

    • Create 3 UDFs as shown in screenshot below

    • Create a Global Change using the the 3 UDFs created above. Remember to replace 19-Jul-99 with your project start date and apply the Global Change

    • Add 2 columns to your schedule for Start Day & Finish Day using the UDFs user_integer_1 & user_integer_2

    • Voila, your ordinal dates should now be visible on your schedule

     

    =jerome