Original Duration

Hafiz Khalid HussainMember for 14 years 5 months
Created
6
21
0

Good evening everybody,

I want to filter only those activities having EVEN (Multiple of 2) original duration throughout the schedule. Can someone give me the trick for that kind of filter or grouping?

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Create UDF for the result of

    Create UDF for the result of Orig Dur/2 THEN filter using UDF that does not contain .5
  2. 0
    Raymund de Laza ·

    Create UDF for the result of

    Create UDF for the result of Orig Dur/2 THEN filter using UDF that does not contain .5
  3. 0
    Zoltan Palffy ·

    since you should not have any

    since you should not have any durations over 20 working days then 

    filter all

    where original duration is not equal to 1

    where original duration is not equal to 3

    where original duration is not equal to 5

    where original duration is not equal to 7

    where original duration is not equal to 9

    where original duration is not equal to 11

    where original duration is not equal to 13

    where original duration is not equal to 15

    where original duration is not equal to 17

    where original duration is not equal to 19

  4. 0
    Dody Sujasman ·

    Dear Professionals,total

    Dear Professionals,
    total original duration on WBS does not represent total duration in detail of its activity ..
    how to fix it?
     
    Thanks,
    Dody.S
  5. 0
    Zoltan Palffy ·

    dody I will not answer this

    dody I will not answer this becasue you stepped on someone elses thread. If you have a question create a new post and ask it. You question has NOTHING to do with the original question.

  6. 0
    Zahid Shaikh ·

    Just curious why are you

    Just curious why are you looking to filter that? Any specific situation that is requiring you to filter activities with that duration?