Program to complete works beyond the Contractual Time to Complete.
- Created
- 3
- 5
I am working as an Engineer for a Building Project.
Our Contractor has failed to complete the Works within the Contractual Time for Completion. The delays are solely attributed to the contractor.
Now, we would like to receive from the Contractor, his programme to complete and hand over the works to the Client. What will this program be called? Under which contract clause of FIDIC 1987, can this be asked? Is there a similar in any standard form of contract to ask for a program to complete outstanding works beyond the contractual completion date?
I think, this cannot be called as a Revised Program, as the time for completion has already elapsed?
Thanks and Best Regards.
Jose VA
3 replies