Manpower loading

Vigeeth SalianMember for 10 years 7 months
Created
2
3
0

hi,

guys i have 30activities, which is finish to start.

and i have only 2men to complete all 33 activities.

how can i allocate just 2men.

My total manpower after allocation should show me 2men.

 

Thanks & Regards,

 

Vigeeth

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi VigeethJust allocate 2 men

    Hi Vigeeth

    Just allocate 2 men to each of the tasks - when the logic is FS with no lead lags the histogram should show a straight line of 2 men allocated.

    Best regards

    Mike Testro

  2. 0
    Vladimir Liberzon ·

    Assign those who will do the

    Assign those who will do the work, enter resource availability (two men) and then level project resources.

    The software will organize the sequence of work so that at any time not more than two men will be used. It does not matter if your activity dependencies are FS or others, or no dependencies at all.

Log in or join to reply