Report: Current Week Activities

Stefano SquadraniMember for 10 years 4 months
Created
4
3
0

Hello Guys,

I would like to create a report that displays the to-do list of the acitvities grouped by project of the current week, supposed that I run the report on monday. I cannot manage to create it. How can I make it?

 

Thank you

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Stefano, it depends on the

    Stefano, it depends on the software that you use.

    In Spider Project you just select the period and that's all. It is standard function.

  2. 0
    Robert Bell ·

    Hi Stefano, You can do this

    Hi Stefano,

    You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

  3. 0
    Robert Bell ·

    Hi Stefano, You can do this

    Hi Stefano,

    You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

  4. 0
    Raymund de Laza ·

    Hi,Suggests to assign

    Hi,

    Suggests to assign activity codes to use for grouping and filter using Current Day+7d

     