Remaining Late Units before Data Date

Daryn SultanbekMember for 14 years 11 months
Created
1
2
0

Hi everyone,

I was updating the progress. Wanted to extract actual & remaining labour units from primavera P6 R8.2in order to create Actual & Forecast curves.

I checked the forums, tried some options like:

- Negative Float - I have none

- Constraints - There are no constraints in the schedule, there is one Project constraint where you have to put Must Finish by x date. That comes after couple of months Early Finish Date.

My schedule still has Cumulative Remaining Late Units.

What do I do? Any advice would be appreciated.

1 reply

Oldest first
  1. 0
    Islam Thabet ·

    THEN COPY FROM XER TO EXCEL

     

    THEN COPY FROM XER TO EXCEL DATA SHEET

    I hope you find the right answer in this Pic.