Actual Units Update Issue
In the Open Standard
John VadasseryMember for 10 years 2 months
- Created
- 4
- 3
0
While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press schedule, the actual units go back to the earlier value instead of showing the updated value. Does anyone know why this happens?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?