Actual Units Update Issue

John VadasseryMember for 10 years 2 months
Created
4
3
0

While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press schedule, the actual units go back to the earlier value instead of showing the updated value. Does anyone know why this happens?

4 replies

Oldest first
  1. 0
    Gema Arenas ·

    Hi John, Have you been able

    Hi John,

     

    Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one.

     

    Thanks

  2. 0
    Zoltan Palffy ·

    what software  ?

    what software  ?

  3. 0
    Prashant Nalawade ·

    Friends,i m also feeling the

    Friends,

    i m also feeling the same problem 

     

    Thanks.

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

  4. 0
    Gema Arenas ·

    I am using P6.When I update

    I am using P6.

    When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite.

     

    Thanks