Skip to content

Filter Activities without FS Relations Only

Arun VasanthMember for 17 years
Created
4
2
0

Dear Friends,

 

I got a program for review .I forgot to filter the activities dont have FS relations .

 

Please help.

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    An answer depends on the

    An answer depends on the software that you use.

  2. 0
    Arun Vasanth ·

    P6 R8.2

    P6 R8.2

  3. 0
    Tom Boyle ·

    Arun,There is not a standard

    Arun,

    There is not a standard layout (nor a standard report) that shows this in P6.

    1. The simplest approach is to export the schedule data to Excel, then autofilter the predecessors list.
    2. If you insist on working inside P6, then
    • Use the Report Wizard to make a new report of "Subject Area" = Activity Relationships, then;
    • In "Configure Selected Subject Areas," apply a filter for, "Where Relationship Type is not equal to FS".
    • You'll also need to add columns to the report to make it readable - e.g. Predecessor Project/ID/Description, Successor Project/ID/Description.

    Good luck, tom

  4. 0
    Rafael Davila ·

    If the Successors and

    If the Successors and Predecessors columns give you information to identify link type a filter should do it very easily.

     photo FS01_zpsdcmuyqxd.png

     photo FS00_zpsljzwajdy.png

    As a word of caution I believe if you only check against predecessors a few activities might be missing. Look in my example for Activity 10 it has no predecessor links, it is on the successor links that non FS links happen.

    Good Luck,

    Rafael

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?