Lag ,Total Float and Duration

Arun VasanthMember for 17 years
Created
2
3
0

Dear Family Members

What is the maximum and minimum Lag allowed in a program??

What is the maximum Activity duration can be allowed in a program??

What is the maximum and total float allowed in a program ??

 

Regards

Arun.V

2 replies

Oldest first
  1. 0
    Kannan CP ·

    Hi Arun,1. For SS+ Lag, the

    Hi Arun,

    1. For SS+ Lag, the lag should not be more than half of  the predecessor duration. Always try to avoid FS+Lag.

    2. Try to limit the construction activities in 21 days, to monitor & control it properly.

    3. Total Float depends on the proper logic in the programme.

     

    BR

    Kannan

  2. 0
    Rafael Davila ·

    There are no such thing as a

    There are no such thing as a universal rules for planning, the rules shall be used only as a guide/warning on possible errors but not to define them as definitive error. Some of these rules might prevent you from creating better models.

    Say concrete placing activity takes 6 hours but curing shall start after the 4th hour; there is a necessary lag that is more than 50% the duration of predecessor. You can bypass such 50% requirement if model lag as an activity.


    Say an activity takes 3 months, common in linear jobs; if you split the activity into separate activities then resource leveling might spread them apart instead of keeping the activity contiguous.

    Float is a calculation, if the software can do the right calculation and the model is good it will be whatever it comes to be.